South Africa George building collapse that killed 34 was preventable, says minister

Workers reported feeling vibrations in the partially built structure, and being told to cover up holes with sand.
Watch LiveBritish Broadcasting CorporationHomeNewsSportBusinessInnovationCultureArtsTravelEarthAudioVideoLiveHomeNewsIsrael-Gaza WarWar in UkraineUS & CanadaUKUK PoliticsEnglandN. IrelandN. Ireland PoliticsScotlandScotland PoliticsWalesWales PoliticsAfricaAsiaChinaIndiaAustraliaEuropeLatin AmericaMiddle EastIn PicturesBBC InDepthBBC VerifySportBusinessExecutive LoungeTechnology of BusinessFuture of BusinessInnovationTechnologyScience & HealthArtificial IntelligenceAI v the MindCultureFilm & TVMusicArt & DesignStyleBooksEntertainment NewsArtsArts in MotionTravelDestinationsAfricaAntarcticaAsiaAustralia and PacificCaribbean & BermudaCentral AmericaEuropeMiddle EastNorth AmericaSouth AmericaWorld’s TableCulture & ExperiencesAdventuresThe SpeciaListEarthNatural WondersWeather & ScienceClimate SolutionsSustainable BusinessGreen LivingAudioPodcastsRadioAudio FAQsVideoLiveLive NewsLive SportHomeNewsSportBusinessInnovationCultureArtsTravelEarthAudioVideoLiveWeatherNewslettersWatch LiveSouth Africa building collapse that killed 34 was 'entirely preventable', minister says23 hours agoShareSaveShingai NyokaBBC NewsShareSaveAFP via Getty ImagesWorkers had reported feeling vibrations in the partially built structure, and being told to cover up holes with sandA building collapse that killed 34 construction workers and injured dozens in Western Cape province last year was "entirely preventable", South Africa's government says.
A new report into the tragedy reveals that serious safety concerns had been raised well before the partially built five-storey apartment block collapsed in the town of George in May 2024.
Public Works Minister Dean Macpherson said the collapse was the result of multiple failures including the use of substandard materials, structural cracks, and visible gaps.
"There were a number of red flags that were continually raised about this project," said a visibly angry Macpherson.
Some of the defects were detected a year before the collapse. The health and safety officer even resigned in protest but work continued, the report found.
https://www.bbc.com/news/articles/c62dj52rp7vo
Rating: 5